Amsterdam Data Center - AMS-3 Electrical Maintenance
Scheduled Maintenance Report for HorizonIQ
Completed
The scheduled maintenance has been completed.
Posted Jun 17, 2017 - 17:08 CDT
Update
We experienced an unexpected power failure event to the entire AMS-3 Data Center, resulting in electrical interruption to all customer servers in this room. Electrical service has been restored and all systems are coming back online. We will continue to monitor this situation closely.
Posted Jun 17, 2017 - 14:47 CDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 17, 2017 - 12:30 CDT
Scheduled
During normal inspection procedures it was found that the UPS system in our AMS3 data center in Amsterdam is in need of an update to ensure stable power is continually supplied to our equipment. This is a part of our facility’s long-term asset management and replacement program. During this event, power will be interrupted to servers and our Data Center Operations teams will install Automatic Transfer Switches and re-energize systems. We anticipate total downtime to be around 1 hour.
Posted Jun 17, 2017 - 12:21 CDT