Chicago Data Center - Non-Impacting Emergency Network Maintenance
Scheduled Maintenance Report for HorizonIQ
Completed
The scheduled maintenance has been completed.
Posted Mar 11, 2018 - 03:34 CDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 11, 2018 - 00:00 CST
Scheduled
Engineers will be conducting emergency software upgrades to an aggregation stack within the private network, to address recent service stability concerns. Redundant network paths are in place and connectivity is expected to remain uninterrupted while the action is performed. The window will last 5 hours, but there is no expected impact to network connectivity in any way. Clients affected by this maintenance window will receive a direct notice with a list of servers related to the event.
Posted Mar 10, 2018 - 01:32 CST
This scheduled maintenance affected: Bare Metal and Dedicated Cloud Services (Chicago).