Planned Hardware Maintenance : APC Replacement
Incident Report for SingleHop
Resolved
This emergency maintenance is now complete. Service is 100% restored.
Posted 2 months ago. Jul 12, 2018 - 00:11 CDT
Investigating
During this maintenance, we will bring each affected server offline in cab 14.22 on PDU B, remove power, and replace the PDU. Expected downtime is 30-60 minutes, though the window is 2 hours to accommodate for any unforeseen circumstances. We will then ensure each server comes back online properly after the move.
Posted 2 months ago. Jul 11, 2018 - 21:58 CDT
This incident affected: Data Centers - Network and Power Uptime (CHI-3).