Amsterdam Data Center - AMS-3 Electrical Maintenance
Scheduled Maintenance Report for HorizonIQ
Completed
The scheduled maintenance has been completed.
Posted Aug 11, 2017 - 18:52 CDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 11, 2017 - 17:01 CDT
Scheduled
During a previous power maintenance in June, all cabinets in our AMS3 Data Center were moved to dual power feeds behind ATS systems as the UPS system was removed and replaced. We are now planning to move power from the temporary UPS to the permanent one.

We have tested our ability to seamlessly switch between the A and B feeds under the new equipment, and through extensive audits, we expect no downtime to occur as A and B side power will not be simultaneously removed.

While performing this type of work presents the possibility of an unforeseen situation to arise, every effort is being made to ensure this will be a non impacting maintenance.
Posted Aug 11, 2017 - 16:50 CDT