CHI-3 UPS Preventative Maintenance
Scheduled Maintenance Report for SingleHop
Completed
The scheduled maintenance has been completed.
Posted 12 days ago. Dec 04, 2018 - 17:00 CST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 12 days ago. Dec 04, 2018 - 07:01 CST
Scheduled
INAP Operations team along with INAP preferred vendors will be performing preventative UPS maintenance.
This work will require critical loads to be transferred between sources at various times.
Conditioned UPS power and back-up power systems will be available at all times during this maintenance.
This work is designed to be transparent to your operations, and no impact is expected.
Posted 17 days ago. Nov 29, 2018 - 08:55 CST
This scheduled maintenance affected: Data Centers - Network and Power Uptime (CHI-3).